Show ApplicationProcessingDetails

Id: 25348337
Approve: false
Approve Note:
Clarification: false
Clarification Note: 1. As per CPCB guiddelines of March 2023, we will install Effluent Treatment Plant (ETP) of capacity 10 KLD with collection tank, oil and grease trap followed by physico-chemical treatment shall be provided for the treatment of wastewater generated from floor/vehicle washings, including rainwater in compliance with health and environmental regulations. 2. We will also complied all other guidelines issued by CPCB for ELV, 2023 at the time of obtaining Consent to operate from the board.
Date Created: 2024-04-04 16:26:22.887
File Note: 1. As per CPCB guiddelines of March 2023, we will install Effluent Treatment Plant (ETP) of capacity 10 KLD with collection tank, oil and grease trap followed by physico-chemical treatment shall be provided for the treatment of wastewater generated from floor/vehicle washings, including rainwater in compliance with health and environmental regulations. 2. We will also complied all other guidelines issued by CPCB for ELV, 2023 at the time of obtaining Consent to operate from the board.
Inspection: false
Inspection Note:
Officer: O24SAS815219
Reject: false
Reject Note:
Role: Industry