| File Note: |
The application of the industry has been scrutinize and it is observed as under:
1. There is an increase the cost of fixed asset of the units from 585.81 crores to 621.6 crores especially w.r.t building cost and plant and machinery. The industry has submitted balance sheet which is not readable and additionally the addition of cost of 35 cr. is to be bifurcated under the heads of building, plant and machinery and then submitted in this office. Therefore, the industry is requested to intimate the details about the increase in the cost of fixed assets and also submit revise building plan (in case of new additions).
2. The industry was granted CTO for discharge of trade effluent @430 KLD and domestic effluent @370 KLD onto land for plantation and the industry has now applied for discharge of different quantities of trade as well as domestic effluent along with change of mode of disposal. The matter was discussed with the representative of the industry he confirmed that the mode of disposal has changed. Therefore, the industry is required to submit varied application instead of renewal application.
3. The water balance submitted in the application reflects that cooling water consumption and generation is the same and requires clarification. Further, it is also requested to submit water balance.
In view of above mentioned facts, if approved the application may be returned with the request to re-submit the same after attending to the aforesaid observations.
|