Clarification Note: The application of the industry has been scrutinized and it was observed as under : - 1. The PP has not attached the layout plan approved from the Competent Authority. 2. The PP has considered population of 5 resident per plot while calculating sewage generation instead of 15 considering 3 floors. As such the capacity requires to be amended. As such you are requested to clarify the above said observations within 2 days so that the application can be processed further.