| Clarification Note: |
The application submitted by the project proponent has been scrutinized and it was observed as under:
1. The project proponent has proposed to discharge 10 KLD onto land for green area (1767 sqm) only for summer season. However, the project proponent has not submitted season wise water disposal detail in green area (1767 sqm).
2. The project proponent has proposed to discharge 30 KLD onto land for irrigation in an area of 905 sqm to be developed as per Karnal technology and same is not adequate.
3. The project proponent has proposed to install mechanical evaporator of capacity 10 KLD for disposal of treated wastewater 50 KLD (and 60 KLD in rainy season). However, the project proponent needs to submit feasibility report / detail drawing/ design etc. regarding the same.
It is requested to submit the reply to the clarification within 02 days. Until then, the application will be treated as incomplete. |