| File Note: |
Sir, it is submitted that there is no MAH unit within the 250 mtr boundary of the project. Further, the site is surrounded by other industrial unit such as M/s Golden Moment Breweries Pvt. Ltd., M/s ECO Spin Yarns, Brick Kilns and other industries.
The project proponent has submitted copy of DTP letter no. 2240 dated 23.11.2022 as per which the site falls in industrial zone as per Land Use Plan, Lalru (copy enclosed). Further, as physically observed there is no village phirni/residential area/15 pucca houses or drain within the 100 mtr boundary of the project and as such the site is suitable for setting up of the unit as per Board’s policy dated 30.04.2013.
In view of the above, it is recommended that “Consent to Establish” (NOC) under the Water (Prevention & control of Pollution) Act, 1974 and the Air (Prevention & Control of Pollution) Act, 1981 may be granted for one year subject to suitable conditions and additional conditions that:
1. The industry shall not start any construction activity without obtaining prior environmental clearance for the propose project.
2. The NOC/ CTE has been granted on the basis of information and undertaking filed by the project proponent and if, in future any information is found wrong, the Board has right to revoke the NOC/ CTE and take penal action against the project proponent and its responsible person. The Punjab Pollution Control Board shall not be responsible for any financial liability and /or any other liability of the project proponent due to grant of this consent to establish.
3. The industry shall apply for obtaining consent to operate under the Water (Prevention & Control of Pollution) Act, 1974 and the Air (Prevention & Control of Pollution) Act, 1981 before commissioning of its unit.
4. The industry shall give complete drawing and design of ETP at the time of consent to operate.
5. The industry shall obtain change of land use for the concerned authority, if need be.
6. The project proponent shall submit approved building plan from the competent authority alongwith the applications for consent to operate.
7. The industry shall obtain permission from PESO for storage of methanol before commissioning of the unit.
8. The industry shall comply with the various by-laws of Master Plan, Derabassi.
9. The industry shall obtain permissions from other concern departments, if need be.
10. The industry shall not discharge the effluent into any drain/choe/nallah, in any case.
11. The industry shall not discharge any effluent at any unauthorized place by any unauthorized means i.e. shall not discharge any wastewater in any drain / inland surface waters / drain/choe/nallah/ onto land for stagnation or outside its premises, at any time, under any circumstances.
12. The industry shall ensure that the activity of unit does not create any nuisance in the surrounding areas and no public complaints are received.
13. The industry shall ensure the compliance of provisions of the Water (Prevention & Control of Pollution) Act, 1974, Air (Prevention & Control of Pollution) Act, 1981, Environment (Protection) Act, 1986 and/or any other environmental law applicable to him and Rules, Circulars & Directions issued by the Board from time to time.
14. In case the project proponent fails to comply with the provisions of the Water (Prevention & Control of Pollution) Act, 1974, Air (Prevention & Control of Pollution) Act, 1981, Environment (Protection) Act, 1986 and/or any other environmental law applicable to the project and Rules, Circulars & Directions issued by the Board from time to time, action as deemed fit shall be taken against the project proponent.
Competency: Senior Environmental Engineer
|