| File Note: |
Pl submit reply to point no. 2 w.r.t consent fee as already raised vide undersigned note dated 23.04.24.
Recheck quantity of fuel to be used in boiler- 1.5-2 Ton/ day doesn’t seems to be correct
Was stack of boiler clear as already asked vide undersigned note dated 23.04.24.
Pl request industry to submit completion certificate w.r.t ETP mentioning capacity, technology and whether ETP will achieve prescribed standards of the Board as already asked for vide undersigned note dated 23.04.24.
Has assurance to submit building plan within a month, is given in writing by the industry ?
Pl address all abovementioned observations and re-submit the application. |