Show ApplicationProcessingDetails

Id: 25493316
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2024-04-24 14:53:33.776
File Note: In view of note and recommendations of AEE/EE RO FGS the industry has not complied with decisions of the personal hearing dated 17.11.2023 as the industry has not submitted the proposal regarding control of secondary emissions generated from the process. As such, may if approved the application for renewal of consent to operate under the Air Act, 1981 applied by the industry be refused after affording an opportunity of personal hearing before the Competent Authority of the Board. Scale – Medium (Orange) Date of Receipt – 18/03/2024 Date of Scrutiny –20/03/2024 Date of visit- 29/03/2024 Date of Deemed Approval – 06/05/2024 (30 working days) Competency – CEE
Inspection: false
Inspection Note:
Officer: PPCB103
Reject: false
Reject Note:
Role: ZO EE Amit Kumar