| File Note: |
The point wise reply of queries is as under:-
1. STP of 100 KLD is adequate is for the project or not.
Reply: The exact calculation regarding proposed discharge has not submitted by the project proponent.
2. Permission obtained from MC to discharge effluent into sewer after.
Reply: No permission has been obtained/submitted from MC to discharge effluent into sewer after
3.. As per Punjab Pollution Control Board office order no. 315 dated 05.07.2018 regarding installation of sewage treatment plants for residential/commercial complexes/construction projects proposed to be established/being established, it was decided as under: “If the residential colony/commercial complex/construction project is proposed to be established within the municipal limits of a City/Town of the State and it proposes to discharge its entire sewage into the municipal sewer, then the promoter of the residential colony shall install adequate and appropriate individual sewage treatment plant. The project proponent shall make arrangements to re-use the treated effluent for flushing purposes and/or for watering of green areas in the project premises. Only the surplus treated waste water shall be discharged into the MC sewer.”
Reply:No details of proposals for arrangements to re-use the treated effluent for flushing purposes and/or for watering of green areas in the project premises has been submitted.
4. Disposal of solid waste and its disposal
Reply: No details of solid waste and its disposal has been submitted.
Submitted for further necessary action, please.
|