Show ApplicationProcessingDetails

Id: 25529439
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2024-04-29 15:32:21.337
File Note: The project proponent has developed adequate plantation area and has also provided plantation along the boundaries of the project. Also the project proponent has provided vertical gardening in the mall. As per current record about 40 KLD is being treated daily in the STP and 25-30 KLD is being used for gardening and dual plumbing, 2-3 KLD is being used for HVAC makeup and the rest is being discharged into sewer. As per record the water extraction and generation is well within the EC. The compliance of the other EC conditions verified by this office is also attached. Submitted as per earlier recommendations please.
Inspection: false
Inspection Note:
Officer: PPCB127
Reject: false
Reject Note:
Role: RO AEE Ravdeep Singh