Date Created: 2024-04-30 11:13:28.772
File Note: As discussed, the industry has already obtained consent to operate under the Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981 for manufacturing of Captive Power Plant of capacity 15 Megawatt and now applied for its renewal. Hence, it is recommended that consent to operate under Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981 may be granted upto 31/03/2029. Scale – Large (Red) Date of Receipt – 28/03/2024 Date of Scrutiny – 08/04/2024 Date of visit- 12/04/2024 Date of Deemed Approval – 17/05/2024 Competency – Chairman of the Board Submitted please
Inspection: false
Inspection Note:
Officer: PPCB118
Reject: false
Reject Note:
Role: RO AEE Malkit Singh