| File Note: |
As discussed, the industry has already obtained consent to operate under the Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981 for manufacturing of Captive Power Plant of capacity 15 Megawatt and now applied for its renewal. Hence, it is recommended that consent to operate under Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981 may be granted upto 31/03/2029.
Scale – Large (Red)
Date of Receipt – 28/03/2024
Date of Scrutiny – 08/04/2024
Date of visit- 12/04/2024
Date of Deemed Approval – 17/05/2024
Competency – Chairman of the Board
Submitted please
|