| File Note: |
The application of the Project Proponent has been scrutinized and it was observed that the Project Proponent has submitted feasibility report regarding installation of STP, in which it has not mentioned flow chart as well as character of effluent before treatment and after treatment. The Project Proponent has proposed different components, but no dimension as well as retains effluent for treatment has not been mentioned. As such, scheme proposed has not been adjudge to adequate or not. Further, the Project Proponent has not submitted any concrete plan for disposal of treated wastewater viz-a-viz area / land for disposal.
The Project Proponent has proposed compost pits for disposal of wet waste, but not proposed any scheme for disposal of dry waste.
The PP was requested telephonically to submit compliance of the above said observations. But, it has failed to submit till date. If approved, application of the Project Proponent may be returned please.
|