Date Created: 2024-04-30 14:39:06.74
File Note: It is submitted that the project proponent has developed roads, laid sewer network, storm network, water supply network within the project. The project proponent has provided boundary wall around some sides of the project. No construction of any residential house has been started at the project. During visit no construction work was carried out as such no labour was available at the site. The project is a residential plotting project in an area of 8.75 acres as such not covered under the EIA notification 14.09.2006.No STP work has been started at the project site. Submitted for approval as recommended above please.
Inspection: false
Inspection Note:
Officer: PPCB138
Reject: false
Reject Note:
Role: RO AEE Vipin Kumar