| Id: | 25572137 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2024-05-03 09:39:00.351 |
| File Note: | It is submitted that the note of AEE is perused and Regional Office is required to clarify the following observations: 1. Reason for increase in the fixed assets. 2. Water balance/ audit of the industry with record of fresh water consumption as well as disposal of the effluent to be submitted. 3. Use/ treatment/ disposal of the water used in quenching of material. 4. Type of polymer being used in quenching, disposal of the containers and faction of the polymer in the said process. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB103 |
| Reject: | false |
| Reject Note: | |
| Role: | ZO EE Amit Kumar |