Show ApplicationProcessingDetails

Id: 25775733
Approve: false
Approve Note:
Clarification: true
Clarification Note: It is intimated that the project proponent needs to submit approved layout plan earmarking the location of evaporator to be installed. The project proponent needs to submit detail whether the cost of evaporator is included in the total cost of project or not. Further, the project proponent has proposed to install steam based evaporator, however, has not submitted feasibility report of boiler, location of boiler, fuel to be used in boiler, whether boiler is permitted in the said zone. Further, the project proponent has submitted in the feasibility report, that the evaporator will be used to evaporator high TDS treated wastewater, however, has not submitted source of generation of high TDS effluent, whether the project proponent is also installing RO system or not. It is requested to submit the reply to the clarification within 02 days. Until then, the application will be treated as incomplete.
Date Created: 2024-05-27 17:48:46.54
File Note:
Inspection: false
Inspection Note:
Officer: PPCB106
Reject: false
Reject Note:
Role: RO AEE Gulshan Kumar