| Id: | 25778767 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | Discussed with Competent Authority, though the site is industrial as per Master Plan, but the project proponent needs to submit letter regarding exemption from SAC from concerned authority. You are requested to submit the same within 03 days. |
| Date Created: | 2024-05-28 10:53:05.885 |
| File Note: | Discussed the matter with CEE, |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB092 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Deepak Chadha |