| Clarification Note: |
On scrutinizing the application, it is observed as under:-
1) The project proponent has mentioned 05 number residents / residential plot in the feasibility report and accordingly has calculated the consumption and generation of wastewater. Further , the water consumption per person per residential plot has been mentioned as 135 ltrs/day. However, as per Department of Housing and Urban Development notification issued vide no. G.S.R. 144/P.A.11/1995/Ss.180 and 43/2021 dated 31.08.2021 circulated by the Board vide Head Office letter no. 15864-82 dated 22.07.2022, it has been specified that the population of plotted development shall be counted @ 15 persons per plot, hence the calculation of water pollution load as well as the disposal arrangements proposed by the project proponent is not adequate.
2) The project proponent is required to submit details of the plantation area / green area to be developed in the colony premises for discharge of treated wastewater.
3) The project proponent is required to submit change of land use certificate issued by the concerned authorities.
Kindly clarify the above said observations within 02 days.
|