Show ApplicationProcessingDetails

Id: 25785595
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2024-05-28 17:11:45.272
File Note: Sir, the project proponent has not mentioned clearly the generated water recycled or utilization in plantation area. The project proponent has not submitted any pocket wise detail regarding utilization of treated effluent. The project proponent has not submitted any permission for water extraction from the concerned department. If approved, application may be returned the project proponent with request to reapply after removing the above said observations please.
Inspection: false
Inspection Note:
Officer: PPCB133
Reject: false
Reject Note:
Role: RO AEE Jatinder Kumar