| File Note: | Sir, the project proponent has not mentioned clearly the generated water recycled or utilization in plantation area. The project proponent has not submitted any pocket wise detail regarding utilization of treated effluent. The project proponent has not submitted any permission for water extraction from the concerned department. If approved, application may be returned the project proponent with request to reapply after removing the above said observations please. |