| File Note: |
After perusal from Regional Office report, may, if approved, Environmental Engineer, Regional Office be requested to submit the clarification on following point in annotated form:
1. The industry shall dismantle the steam and electric connection of the excess machinery having discharge beyond the shares which have been DEMAT. These excess machines shall be sealed by the Regional Office of the Board till the industry obtains CTE/CTO for the same……………………..
2. The industry shall submit the following documents within 7 days:
a) The industry shall submit data regarding abstraction of ground water / fresh water supply for the last three months. It shall provide EMFs on all sources of fresh water if not provided earlier…………..
b) The industry shall earmark on map the location of all active / closed submersible pumps fresh water sources……………….
c) Details of dyeing machinery / other water consuming machinery along with specifications including production capacities specifying liquor ratio, number of lots, water consumption per lot, thus calculating the total fresh consumption (with duly authenticated). ……………
d) Numbers of shares held by the industry (duly certified by the SP) along with NOC from PDA / SPV regarding proposed discharge into common sewer of CETP…………………….
e) The industry shall get its shares DEMAT and submit the documentary evidence in this regard. By the time, the DEMAT process is completed, the industry shall submit a certificate from Company Secretary of the PDA for the shares that have been recommended to the ROC for DEMAT…………….
f) Record of discharge during the last three months as per SCADA. g) NOC from the PDA allowing quantum of discharge into the common conveyance system of CETP of 50 MLD capacity………………. 3. The industry shall install EMF meter at extraction points i.e. tubewell and final out to CETP, within one month and connect the same with SCADA system. …………………….
4. It was made clear to the industry that in case it is again found operating beyond the DEMAT capacity, without prior permission of the Board, strict action may be taken which may include closure without any further notice/ opportunity of personal hearing………………………..
Further EE, RO to explain the reason to process the case after 02 months.
Submitted for approval, please. |