Show ApplicationProcessingDetails

Id: 25947624
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2024-06-18 13:10:05.104
File Note: The application of the brick kiln was scrutinized and it was observed that the brick kiln has not submitted the coal register from 01.02.2019 up to the completion of the brick kiln into Zig zag technology. A Clarification was raised on 12/06/2024 to submit the reply of the observation within 03 days. But till date no reply has been submitted by the brick kiln. In view of the above, may if approved, the application of the brick kiln be returned with request to resubmit the same after attending above said observations please.
Inspection: false
Inspection Note:
Officer: PPCB122
Reject: false
Reject Note:
Role: RO AEE Vinod Kumar