| File Note: |
The application of the industry is scrutinized and found incomplete due to the observations made as under:
1. The name of the project is to be corrected.
2. The Tehsil needs to be corrected.
3. The communication details is not mentioned.
4. The project cost is not given. As such, adequate consent fee cannot be ascertained.
5. The area of project is not as per Environmental Clearance granted.
6. The project is mentioned to be located within MC limits.
7. The date of commissioning is given as January 2024.
8. Many of the column has been left blank.
9. The raw material is not as per Environmental Clearance.
10. No source and quantity of water is given for water sprinkling.
11. The wastewater treatment is not mentioned.
12. Source of Air Pollution / dust emission and its control is not given.
13. The mining lease area, Khasra no. and other components mentioned in the Environmental Clearance are not in consonance with that mentioned in the mining plan.
14. Following documents are not submitted:
a. Authority letter.
b. Appropriate / complete compliance report of EC granted.
c. Compliance of conditions of approval of mining plan letter.
d. CA certificate.
Therefore, the application of the project cannot be processed and may please be returned to it.
|