| File Note: |
The note of RO may kindly be perused…….
The industry is a small scale red category dyeing unit and was granted consent to operate under the Air (Prevention & Control of Pollution) Act, 1981 vide no. CTOA/Renewal/LDH3/2023/22946045 dated 21.08.2023 having validity upto 20.08.2024…..
Now, the industry has applied for varied consent to operate under the Air Act, 1981 for dyeing of acrylic Yarn/ fancy yarn @ 3000 Kg/day in 02 shifts ……….
The industry has deposited adequate fee upto 30.06.2029 and requisite documents as verified by the RO……
RO has reported that the industry has submitted the certificate of DTP letter vide no. 1743/DTP(L)-M2A dated 20.06.2019, which is stating that the unit is falls in the industrial Zone as per approved Master Plan, Ludhiana……..
RO has reported that the industry has now increased its production capacity by increasing 01 shift as earlier the industry was operating only in single shift of 12 hrs and now industry has proposed to operate in 02 shifts of 12 hrs each…….
The industry has not added any wet machinery but it has added plantation area to manage quantum of increased discharge………...
The industry has submitted copies of land documents of entire area including plantation area as verified by the RO……….
The industry was visited by officer of this office on 05.06.2024 and it has been reported as under:
1. The industry was in operation and engaged in the process of dyeing of yarn.
2. The industry has installed 12 cabinet machines of capacity 90 kgX1, 60 kgX4, 45kgX3 and 30 Kgx4 inside the premises for the dyeing of yarn.
3. The industry has installed one no. boiler of 3.0 TPH and provided cyclone separator as APCD. The industry is using rice husk as fuel and also provided adequate stack height with the boiler. The stack was almost clear and no black smoke was observed for the industry during visit.
4. During visit, air emission sampling of the industry was carried out and as per the analysis report received from the zonal lab, concentration of SPM was found 267 mg/Nm3 against the limit of 500mg/ Nm3, hence same was found within the limits prescribed by the Board.
5. The industry has also installed one DG set of 180 KVA with canopy and adequate stack height. 9. The industry is complying with the provisions of Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981.
In view of above, as proposed by RO, it is recommended that varied consent to operate under Water (Prevention & Control of Pollution) Act, 1974 for dyeing of acrylic Yarn/ fancy yarn @ 3000 Kg/day in 02 shifts may be granted to the industry upto 30.06.2029 with the suitable conditions.
Competency: SEE
|