| Id: | 26157024 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | 1. Phone No. may be updated from your office as per e-mail sent 04-07-2024 2. Cost of plant and machinery is correct as per CA Certificate. 3. Authority letter uploaded. 4. Complete compliance report of previous consents uploaded. 5. Complete compliance report of all observation of previous visit already uploaded. 6. Point wise compliance to CPCB guidelines uploaded. |
| Date Created: | 2024-07-06 15:48:48.12 |
| File Note: | 1. Phone No. may be updated from your office as per e-mail sent 04-07-2024 2. Cost of plant and machinery is correct as per CA Certificate. 3. Authority letter uploaded. 4. Complete compliance report of previous consents uploaded. 5. Complete compliance report of all observation of previous visit already uploaded. 6. Point wise compliance to CPCB guidelines uploaded. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | R12RPN39686 |
| Reject: | false |
| Reject Note: | |
| Role: | Industry |