| Id: | 26294652 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2024-07-19 11:03:28.966 |
| File Note: | Sir, the application of the industry has been scrutinized and found complete. However, the industry has not deposited penalty fee under the Water Act, 1974 and the Air Act, 1981 due to late applying of applications (within time period of 9-12 months from date of its commissioning). As such, the clarification may be raised to the industry to deposit the penalty fee within 2 days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCBOS58 |
| Reject: | false |
| Reject Note: | |
| Role: | RO JEE OS Gursewak Singh |