| File Note: |
After discussed. The establishment has applied for obtaining fresh consent to operate under the Water Act, 1974 and Air Act, 1981 for operation of its hotel (14 rooms), restaurant of capacity 50 persons and 1 no. party hall of capacity 50 persons under green category i.e 3052-Hotels (up to 20 rooms and without boilers) and having waste water generation < 10 KLD and no hazardous waste generation.
The water requirement / wastewater generation of the establishment is as under:
a) Total rooms = 14 no.(28 persons)
b) Banquet halls = 1 nos. (50 persons)
c) Restaurant hall = 1 no. (50 persons)
d) Staff = 7 no.
e) Total persons = 135 nos.
Water requirement:
(28 x 180)+ (50 x 70) + (50 x 45) + (7 x 45) = 4.3 KLD + 2.8 KLD + 1.8 KLD +3.1 KLD = 11.15 KLD
Total wastewater generation = 11.15 x 0.8 = 8.8 KLD
The point wise compliance of the Board’s circular no. 64 dated 2/2/2021 is as under:
1. Water Pollution
1.1 Effluent Treatment Plant
a) The Hotel is discharging its domestic effluent generated from toilet into sewer and which will be directed leading to terminal STP of Shermajra Patiala of capacity 46 MLD. Further, the wastewater generated from the kitchen / washing area is being passed through screen bars followed oil & grease trap and then discharged into MC sewer, leading to terminal STP of Shermajra Patiala of capacity 46 MLD.
i) The establishment has provided screen bars followed oil & grease trap for treatment of wastewater generated from the kitchen in compliance of the Board’s Office Order vide its notification no. 271 dated 10/10/2011.
ii) The establishment is discharging its domestic effluent into MC sewer, which will leads to the terminal STP of Shermajra Patiala of 46 MLD capacity.
iii) Same as mentioned at Sr.no. (ii).
iv) NA being small scale.
b) EP Rules specify effluent discharge norms
i) Not applicable.
ii) The project proponent is yet to submit analysis report.
c) The establishment is discharging its wastewater into MC sewer only.
d) The establishment has provided water meters at the source of fresh water supply.
e) NA, as being connected with Terminal STP of Shermajra Patiala 46 MLD capacity.
f) Same as (c).
g) The project proponent is yet to submit analysis report.
h) Same as (c).
i) Not applicable.
1.2. Ground water abstraction
a) Do not relates to PPCB.
b) Do not relates to PPCB.
c) Do not relates to PPCB.
1.3. Water conservation
a) Do not relates to PPCB.
b) Do not relates to PPCB.
c) Do not relates to PPCB.
d) Do not relates to PPCB.
2.1. Air Pollution
a) The establishment is using charcoal for tandoor and PNG gas for other cooking purpose.
b) Complying, the establishment has provided chimney followed by ducting system for exhaust emissions.
c) The establishment has installed 1 no. DG set of capacity 125 KVA, which is equipped with canopy and stack of adequate height.
d) NA.
2.2. Energy Conservation
a) The establishment has provided solar system for producing hot water.
b) The establishment has installed 1 no. DG set of capacity 125 KVA, which is equipped with canopy and stack of adequate height.
c) The establishment has used only LED bulbs in its premises.
3.0. Consent to establish / Consent to operate
a) Complying, / CTO applying.
b) Not applicable.
c) Not applicable.
4.0. Solid Waste Management
a) The kitchen waste (eatable items) is being disposed off through Hari Bhari and Recyclable/plastic waste is being lifted by MC, Patiala. Moreover, the establishment is using re-useable crockery and glasses during functions to minimize plastic waste generation.
b) Not applicable. Does not fall under the list bulk generators.
c) Same as mentioned at 4.0 (a)
d) The establishment has installed 1 no. DG set of capacity 125 KVA, which is equipped with canopy and stack of adequate height.
e) The plastic / re-recyclable waste is being lifted by MC, Patiala
f) Same as above.
g) Same as above.
h) Same as above.
5.0. Noise Pollution
a) The establishment uses only indoor loudspeakers as permitted upto 10.00 p.m. only.
b) Same as above.
c) Same as above.
d) The establishment has installed 1 no. DG set of capacity 125 KVA, which is equipped with canopy and stack of adequate height.
e) The representative of the establishment informed that no burning of crackers are allowed within the premises.
f) The establishment uses only indoor loudspeakers as permitted upto 10.00 p.m. only.
6.0. Infrastructure issues and other requirement
i) Does not relates to PPCB.
ii) Does not relates to PPCB.
iii) Does not relates to PPCB.
iv) Does not relates to PPCB.
v) Does not relates to PPCB.
vi) Does not relates to PPCB.
Moreover, the Hon’ble NGT while disposing of the matter of O.A. no. 400/2017 titled as Westend Green Society V/s UOI and others has passed orders dated 4/2/2021 and the relevant part of which is reproduced as under:
”ETPs need to be installed by all the big units, not connected to the sewer line.”
However, the subject cited establishment is a Small Scale hotel and has provided screen bars followed by oil & grease trap for treatment of kitchen wastewater and is connected with terminal STP of Shermajra Patiala of capacity 46 MLD.
In view of above, it is found that the establishment is complying with the guidelines for control and enforcement of environmental norms as notified by Board’s circular no. 64 dated 2/2/2021.
Therefore, keeping in view of above mentioned facts and submissions made by the project proponent, it is recommended that project proponent may be granted fresh consent under the Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention and Control of Pollution) Act, 1981 up to 31/12/2028 under green category for operation of its hotel (14 rooms), restaurant of capacity 50 persons and 1 no. Party hall of capacity 50 persons with usual conditions and special conditions that: -
1. The project proponent shall maintain the record of water meter on the source of its fresh water.
2. The project proponent shall comply with the guidelines of Punjab Water Regulation and Development Authority (PWRDA), issued for the abstraction of ground water from time to time.
3. The project proponent shall not use any unauthorized mode for disposal of treated/untreated wastewater.
4. The project proponent shall regularly get cleaned the oil & grease trap, so that the wastewater can be effectively treated in the septic tank and the Oil & Grease so removed shall be disposed of in an environmentally sound manner.
5. The adequacy & efficacy of the waste water treatment system will be the entire responsibility of the establishment.
6. The establishment shall conform to the standards for treated waste water as laid down by the Board in circular vide no. SEE (HQ-1)/F.244/2011/271 Dated 10.10.2011.
7. The project proponent shall continue to comply with the provisions of the Solid Waste Management Rules, 2016 for disposal of solid waste generated from the hotel.
8. The industry shall ensure segregation of the solid waste at source, facilitate collection of segregated waste in separate streams, handover recyclable material to either authorized waste pickers or authorized recyclers as prescribed in Solid Waste Management Rules, 2016. The bio-degradable waste shall be processed, treated and disposed of through composting or bio-methanation within the premises as far as possible. The residual waste shall be given to the waste collectors or agency as directed by the local body.
9. The project proponent shall comply with the Mechanism/ guidelines prescribed by the Board vide officer order no. 64 dated 02/02/2021 in true letter & spirit.
10. The establishment shall comply with the provisions of Noise Pollution (Regulation & Control) Rules 2000.
(Competency- Environmental Engineer)
|