| File Note: |
The note of Regional Office may kindly be perused……………………………
The industry is a small-scale red category dyeing unit and was granted consent to operate under the Water Act, 1974 vide no. CTOW/Varied/LDH3/2024/25227033 dated 30.05.2024 for dyeing of yarn/fiber @ 3650 Kgs/day with trade effluent generation @ 338.0 KLD & domestic effluent @ 1.0 KLD into conveyance system of CETP 50 MLD, which is valid upto 29.05.2025…………………………….
Now, the industry has applied for varied consent to operate under Water Act, 1974 for dyeing of yarn/fiber @ 3650 Kgs/day with trade effluent generation @ 337.8 KLD & domestic effluent @ 1.2 KLD into conveyance system of CETP 50 MLD…………………………….
The industry has deposited consent fee, which is adequate upto 30.06.2029 as verified by the Regional Office……………………………..
The industry has submitted the copy of letter issued by DTP, Ludhiana vide memo no. 2691/DTP(L)/ILC dated 24.11.2016 stating that the site of the industry falls in industrial zone as per Master Plan, Ludhiana (2007-2031) ……………………………..
The industry has submitted statement of DEMAT of shares of 339 KLD……………………………..
Regional Office has reported that the industry has applied for varied consent to operate for slightly decreased quantity of trade effluent and increased quantity of domestic effluent but the generation of total waste water remains within the quantum of shares obtained by the industry…………………………….
The industry was visited by AEE of RO on 26.06.2024 and observed that:
1. The industry was in operation during the visit, the industry is engaged in the process of dyeing of yarns/ fabric.
2. The industry has installed 07 cabinet machines of capacities (1 X 240 kgs), (5 X120 kgs), (1 X 60 kgs) and 03 sampling machines inside the premises.
3. As per audit carried out by Guru Nanak Dev Engineering College (GNE) generation of effluent from installed machinery of the industry is 345 ≈ 339, which is within the shares obtained by the industry.
4. The industry has installed emf at source of fresh water extraction point i.e. one submersible.
5. The industry is complying with the provisions of Water (Prevention & Control of Pollution) Act, 1974 conditions of the previously granted consents……………………………..
As proposed by Regional Office, may if approved,
1. Varied consent to operate under Water (Prevention & Control of Pollution) Act, 1974 be granted to the industry upto 30.06.2029 for dyeing of yarn/fiber @ 3650 Kgs/day with trade effluent generation @ 337.8 KLD & domestic effluent @ 1.2 KLD into conveyance system of CETP 50 MLD subject to the condition that:
a) The industry should either take measures to control its inlet parameters by good practices and selection of good chemicals for processing or shall operate and maintain its existing effluent treatment plant (ETP), regularly and efficiently, so as to achieve the inlet effluent standards of CETP as per DPR.
b) The industry shall stop discharging its effluent in case due to any reason the CETP is not operational or dedicated conveyance system is overflowing.
c) The industry shall maintain the record of flow meter installed at outlet leading to CETP.
d) The industry shall not generate/discharge trade & domestic effluent more than 399 KLD.
e) The industry shall not install any new dyeing/ water polluting machinery without permission of the Board.
f) The industry shall discharge the whole consented effluent into dedicate sewer line leading to CETP for final treatment in accordance to the shares allotted to the unit.
g) The industry will also dismantle any other connection available for discharge of effluent either into public sewer or PDA conveyance system.
h) The industry shall make adequate arrangements to minimize the consumption of fresh water………………………………….
Competency-SEE |