Date Created: 2024-08-18 20:54:31.213
File Note: The report /recommendations of Regional Office be perused. The Ro has not submitted comments of siting criteria for establishment of Project as per policy of the Board. It is not clarified that the electric wires are High tension wires or not. The FAR calculations are not submitted. The detail of waste water generation and disposal detail is not submitted. May if approved the case may be forwarded to RO to submit complete detail so as to decide the case accordingly.
Inspection: false
Inspection Note:
Officer: PPCB089
Reject: false
Reject Note:
Role: ZO EE Satyajeet Attari