| File Note: |
The project proponent has applied fresh consent to establish under the provisions of Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981 for establishment of Commercial project in area of 5062 sqm and having total built up area @ 1401 sqm along with requisite documents.
The project proponent has submitted brief project report as per which, the proposed project cost is Rs. 12.50 crore. The project proponent has deposited Rs. 14,900/- vide R no. 973744765 dated 19.11.2024 as NOC fee, which is adequate for 1 year.
The project proponent has submitted feasibility report of the project, and the detail is as under:
Water requirement & Population
Total FAR area at GF floor=1226 Sqm Population on GF @1 person / 3 sqm
1226/3 409 Persons
Total FAR area at FF and SF floor=2612 Sqm Population on FF and SF @1 person / 6 sqm
2612/6 435 Persons
Total 844 persons
Floating population @ 90
% of the total population 760 Persons @ 15lit/ person 11 KLD
Permanent population @
10 of the total population Approximately 84 persons@ 45 lit/person 4 KLD
Domestic Water Required Total 15 KLD
Total Flow to STP@ 80% (Domestic water) 12 M3/day
Flushing 760@ 10 lit/day
84 @20 lit/day
For Construction activity in nearby projects till we get the sewer connection 8M3/day 2 M3/day
2 M3/day
To treat the sewage to an extent that the discharge from the plant will meet the standard norms set by the competent authority. STP of 15 KLD will be provided.
UNITS PROPOSED
Collection Tank, MBBR reactors, Tube settler, Clear water sump, Ultra Filtration and Sludge drying beds
The total solid waste of approximately 169 Kg/ Day and proposed to install 70 Kg/Day mechanical composter.
The garbage to be generated from the COMPLEX is assumed to be of the following types
Household Garbage and Rubbish: Waste from food preparation, sweepings, cleaning, fuel burning, gardening waste, old cloths, waste wood, packaging, ferrous and non ferrous materials etc.
Street Sweepings: Like dirt, litter, drain cleaning, leaves, wood pieces, animal manure etc.
Construction and maintenance debris: This is waste construction material and will be dealt with separately.
The project proponent has submitted LLP agreement made on 04.11.2023 between Mr. Amar Prabhu Goyal, Mr. Abhishek Garg, Mr. Tushar Garg and Mr. Pardeep Garg.
The project proponent has submitted building permit/sanction certificate vide letter no. PB/SAS/ZIRAK/231754 dated 12.10.2024.
The project proponent has submitted sale deed made on 19.09.2024 between Surinder Singh & Others and M/s Meydan Infra LLP Hadbast no. 43.
The site of the project was visited by AEE of this office on 10.12.2024 and during visit, it was observed that:
1. The construction has started and the project is in foundation stage.
2. The project proponent has started construction work of STP of this project at the site.
3. As physically observed, the distance of the proposed site from the various approved existing operational industries / units (for which specific siting guidelines has been issued by the Board for time to time), is more than the required distance as per the siting criteria given as under:
Sr. No. Type of Industrial unit Required distance as per siting criteria
1. Cement Plant /Grinding Unit 300 m
2. Rice Sheller/ Salla Plant 500 m
3. Stone Crushing/ Screening Cum Washing Plant 500 m
4. Hot Mix Plant 300 m
5. Brick Kiln 300 m
6. CBWTF 500 m
7. Poultry Farm 500 m
8. Jaggery Unit 200 m
The site is complying with general siting criteria as per policy dated 30.04.2013 and specific sitting guidelines as per the Department of Science, Technology, Environment, Government of Punjab notification no. 3/6/07/STE(4)/2274 dated 25.07.2008.
4. The project proponent has proposed to install 1 no. DG set of capacity 25 KVA with canopy and adequate stack height.
In view of the above, it is recommended that Consent to Establish (NOC) from pollution angle under the provisions of the Water (Prevention & control of Pollution) Act, 1974 and the Air (Prevention & Control of Pollution) Act, 1981 may be granted for one year subject to suitable conditions and following additional conditions that:
1. The promoter shall not allow any occupancy in the project till the time adequate arrangements for treatment & disposal of wastewater and solid waste are made as well as 'consents to operate' under the Water Act, 1974 & the Air Act, 1981 are obtained.
2. The project proponent shall submit the complete drawing and design of the STP and its component at the time of obtaining consent to operate.
3. The project proponent shall provide separate water meter and energy meter for the STP and maintain record of the same on daily basis.
4. The promoter company shall ensure that the total built up area of all individual projects/plots combined together is not more than 1,50,000 sqm, otherwise the project as such is covered under category 8(b) of the schedule appended to the EIA notification and project proponent of the area development project is required to obtain the environmental clearance, failure which, the promoter company shall be liable for action for the violation of EIA notification dated 14/09/2006.
5. The promoter company shall ensure that the total built up area of construction being carried out by it orany different builders may not be greater than 20,000 sqm, otherwise the project as such is covered under category 8(a) of the schedule appended to the EIA notification and project proponent of the building and construction project is required to obtain the environmental clearance, failure which, the promoter company/builder shall be liable for action for the violation of EIA notification dated14/09/2006.
6. The project proponent shall utilize treated wastewater from nearby STPs for the construction purpose and shall submit an agreement in this regard within one month.
7. The project proponent shall place adequate no. of bins outside its premises from where the Municipal Solid Waste shall be got lifted.
8. The project proponent shall properly handle and manage the solid waste as per the provisions of the Municipal Solid Waste Management Rules, 2016 and ensure that the solid waste is segregated into biodegradable and non-biodegradable components. The biodegradable component shall be treated by providing mechanical composter of adequate capacity to produce compost, which will be disposed of/reused in an environmentally sound manner and the non-biodegradable solid waste shall also be disposed of in an environmentally sound manner.
9. The project proponent shall also ensure that the hazardous waste and e-waste components of the solid waste shall also be segregated and the same shall be channelized to the authorized facility for such type of waste.
10. The project proponent shall comply with the provisions of the Construction and Demolition Management Rules, 2016.
11. The project proponent shall take adequate steps to the effect that the construction material of any kind that is stored at site shall be fully covered in all respects so that it does not disperse in the air in any form.
12. The project proponent shall ensure that all the construction material and debris shall be carried out in trucks or other vehicles which are fully covered and protected so as to ensure that the construction debris or the construction material does not get disburse into the air or atmosphere in any form.
13. The project proponent shall take all necessary steps to control the dust emissions to be generated from the construction activities of the project.
14. The project proponent shall ensure that the vehicles carrying construction material and construction debris of any kind shall be cleaned before it is permitted to ply on the road after unloading of such material.
15. The project proponent shall provide mask to every worker working on the construction site and involved in loading/ unloading and carrying of construction material and construction debris.
16. The project proponent shall provide all medical help, investigation and treatment of workers involved in construction of building and carrying out construction material and debris related to dust emissions.
17. The promoter shall develop its commercial complex strictly in accordance with the layout / building plans approved / to be approved by the Competent Authority.
18. The project proponent shall obtain permission from the PWRDA for the abstraction of ground water if applicable.
19. The project proponent shall install antismog gun to control the dust emission emitted at the time of construction.
20. The NOC is being issued to the project proponent based upon the documents/ information submitted by it alongwith the online application form. The Board would be at liberty to take penal action against the industry/project proponent and its responsible/ concerned person(s) in case information/document is detected as incorrect/false/misleading at any point of time, without any opportunity of Personal Hearing.
21. In case the project proponent fails to comply with the provisions of the Water (Prevention & Control of Pollution) Act, 1974, Air (Prevention & Control of Pollution) Act, 1981, Environment (Protection) Act, 1986 and/or any other environmental law applicable to the project and Rules, Circulars & Directions issued by the Board from time to time, action as deemed fit shall be taken against the project proponent.
*Competency – Senior Environmental Engineer
|