Show ApplicationProcessingDetails

Id: 30825879
Approve: false
Approve Note:
Clarification: true
Clarification Note: While scrutinizing the case, it has been observed that: - 1. The Project Proponent (PP) has not submitted the approval/permission from GLADA and other concerned departments. 2. The Project Proponent has not submitted a feasibility report for the installation of a Sewage Treatment Plant (STP). 3. The Project Proponent has not submitted a proposal for the disposal of treated domestic effluent and details of the area proposed for plantation. 4. The Project Proponent has not submitted a proposal for the disposal of solid waste in accordance with the Solid Waste Management Rules, 2016. You are requested to submit the above said observations within 03 days
Date Created: 2026-01-05 10:05:58.978
File Note: While scrutinizing the case, it has been observed that: - 1. The Project Proponent (PP) has not submitted the approval/permission from GLADA and other concerned departments. 2. The Project Proponent has not submitted a feasibility report for the installation of a Sewage Treatment Plant (STP). 3. The Project Proponent has not submitted a proposal for the disposal of treated domestic effluent and details of the area proposed for plantation. 4. The Project Proponent has not submitted a proposal for the disposal of solid waste in accordance with the Solid Waste Management Rules, 2016. You are requested to submit the above said observations within 03 days
Inspection: false
Inspection Note:
Officer: PPCBOS18
Reject: false
Reject Note:
Role: RO AEE OS Manvinder Singh Hundal