| Clarification Note: |
On scrutinizing the application of the project proponent, it was observed as under:
1. The project proponent required to submit water calculation i.e. water usage, wastewater generation and disposal considering 15 person/ plot as per the NORMS & CRITERIA for Estimation of Population and Water Demand for Building/Construction Projects and Area Development & Townships Projects.
2. The project proponent has required to submit revised proposal for treatment and disposal for the wastewater generated from the project considering 15 person/ plot.
3. The project has attached undertaking that Sh. Jai Singh and Others will provide required land around 0.826 acres (Khasra no. 242 (4-0)) to the project for the disposal of treated wastewater onto plantation.
4. The project proponent has earlier submitted affidavit vide dated 05.10.2023 with Sh. Surinder Singh will provide required land around 4 Bigha 2 Biswe acres (Khasra no. 1153/238, 1159/256, 1151/254) to the project for the disposal of treated wastewater onto plantation.
5. The project has not attached the ownership detail & Aks-chajjra of the said land mentioned Sr. no. 3 & 4.
6. From the affidavit/ undertaking mentioned that preceding paras, it is observed that land for developing plantation as per Karnal Technology has not been rented/ leased. As such the said proposal cannot be considered and the project is required to submit rent deed/ lease deed of both sites for developing plantation as per Karnal Technology.
7. The project proponent needs to apply under orange category (10.1 - Building construction project ≥ 20,000 sq. m. built-up area).
You are therefore requested to submit reply of the above said observation within 1 day.
|
| File Note: |
On scrutinizing the application of the project proponent, it was observed as under:
1. The project proponent required to submit water calculation i.e. water usage, wastewater generation and disposal considering 15 person/ plot as per the NORMS & CRITERIA for Estimation of Population and Water Demand for Building/Construction Projects and Area Development & Townships Projects.
2. The project proponent has required to submit revised proposal for treatment and disposal for the wastewater generated from the project considering 15 person/ plot.
3. The project has attached undertaking that Sh. Jai Singh and Others will provide required land around 0.826 acres (Khasra no. 242 (4-0)) to the project for the disposal of treated wastewater onto plantation.
4. The project proponent has earlier submitted affidavit vide dated 05.10.2023 with Sh. Surinder Singh will provide required land around 4 Bigha 2 Biswe acres (Khasra no. 1153/238, 1159/256, 1151/254) to the project for the disposal of treated wastewater onto plantation.
5. The project has not attached the ownership detail & Aks-chajjra of the said land mentioned Sr. no. 3 & 4.
6. From the affidavit/ undertaking mentioned that preceding paras, it is observed that land for developing plantation as per Karnal Technology has not been rented/ leased. As such the said proposal cannot be considered and the project is required to submit rent deed/ lease deed of both sites for developing plantation as per Karnal Technology.
7. The project proponent needs to apply under orange category (10.1 - Building construction project ≥ 20,000 sq. m. built-up area).
You are therefore requested to submit reply of the above said observation within 1 day.
|