Show ApplicationProcessingDetails

Id: 30875497
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application has been scrutinized and it has been observed that: 1. There is discrepancy in the total water demand mentioned in the application form than in the project report submitted by the Project proponent. Kindly clarify 2. The application has been submitted under the Green category; however, the project report mentions the Orange category. Kindly clarify 3. The PP is required to submit adequate fee i.e. Rs. 6400/year according to the CA certificate submitted by the unit. Therefore the Project Proponent is requested to address above clarifications within 2 days.
Date Created: 2026-01-09 13:14:23.694
File Note: The application has been scrutinized and it has been observed that: 1. There is discrepancy in the total water demand mentioned in the application form than in the project report submitted by the Project proponent. Kindly clarify 2. The application has been submitted under the Green category; however, the project report mentions the Orange category. Kindly clarify 3. The PP is required to submit adequate fee i.e. Rs. 6400/year according to the CA certificate submitted by the unit. Therefore the Project Proponent is requested to address above clarifications within 2 days.
Inspection: false
Inspection Note:
Officer: PPCB205
Reject: false
Reject Note:
Role: RO AEE Kushal Sharma