| File Note: |
Sir, As per the clarification raised by the competent authority of the Board. Point-wise reply as under:-
1. The terminal STP of MC, Longowal of capacity 5 MLD has been installed, which is under stabilization.
2. The project proponent has proposed to consume 653 KLD of fresh water for domestic use, from which it will generate 522 KLD domestic effluent. The sewage generated in the colony will be discharged into sewage treatment plant tank which will install in the premises. After that, it will be reuse in the Dual Plumbing (225 KLD) and disposed 3.0 KLD in park area (6328.89 sqm) in monsoon season & Remaining 284 KLD water is discharged into MC Sewer Line. Whole wastewater will be treated in STP of capacity 550 KLD based on MBBR Technology.
Submitted for approval, please.
Competency CEE
|