Show ApplicationProcessingDetails

Id: 30884956
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2026-01-10 22:01:29.861
File Note: SEE Recommendations for allowing NOC are placed for the approval with following additional conditions:...... 1.....Additional capacity of boiler and thermopac is allowed for facilitating finishing activities only... 1........ There shall be no increase in any wet process as well in existing dyeing machines i.e 10 no. soft flow machines of capacity (4 X 300 Kg), (1 X750 Kg), (3 X 450 Kg) (1 X 150 Kg) and 01 sample soft flow machine, having total 24 chambers............... For approval as above. please ( CETP Member Unit: Competency: Chairperson of the Board)
Inspection: false
Inspection Note:
Officer: PPCB032
Reject: false
Reject Note:
Role: CEE R K Ratra