Show ApplicationProcessingDetails

Id: 30897858
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application was scrutinized and it was obsevred as under:- 1. The industry has not submitted approved layout plan with the application. 2. The industry has submitted completion certificate of ETP installed by it but the capacity and components of installed ETP are not mentioned. You are requested to submit the reply within 02 days pls
Date Created: 2026-01-12 17:17:27.727
File Note: The application was scrutinized and it was obsevred as under:- 1. The industry has not submitted approved layout plan with the application. 2. The industry has submitted completion certificate of ETP installed by it but the capacity and components of installed ETP are not mentioned. You are requested to submit the reply within 02 days pls
Inspection: false
Inspection Note:
Officer: PPCB140
Reject: false
Reject Note:
Role: RO AEE Manmohit Kumar