Show ApplicationProcessingDetails

Id: 30899175
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application was scrutinized and it was observed as under: 1. The unit has not submitted the building plan approved from the Competent Authority. 2. The unit has submitted the distance verification report issued by Tehsildar, Rajpura; however, it has not incorporated the verification of distance of parameters i.e. Village Lal Lakir, Village Phirni and Residential colony or cluster of 15 pucca houses. 3. The unit has deposited the 200% penalty of one year fee under the both Acts; however, the unit is required to deposit additional 100% penalty under the both Acts as the date of commissioning of the unit is 22.12.2023. 4. The unit has not submitted the manufacturing process flow chart. As such, the unit is requested to remove the above said observations within 03 days, so that the application can be processed further.
Date Created: 2026-01-12 21:14:14.244
File Note: The application was scrutinized and it was observed as under: 1. The unit has not submitted the building plan approved from the Competent Authority. 2. The unit has submitted the distance verification report issued by Tehsildar, Rajpura; however, it has not incorporated the verification of distance of parameters i.e. Village Lal Lakir, Village Phirni and Residential colony or cluster of 15 pucca houses. 3. The unit has deposited the 200% penalty of one year fee under the both Acts; however, the unit is required to deposit additional 100% penalty under the both Acts as the date of commissioning of the unit is 22.12.2023. 4. The unit has not submitted the manufacturing process flow chart. As such, the unit is requested to remove the above said observations within 03 days, so that the application can be processed further.
Inspection: false
Inspection Note:
Officer: PPCB123
Reject: false
Reject Note:
Role: RO AEE Pritpal Kaur