Show ApplicationProcessingDetails

Id: 30908050
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2026-01-14 10:14:49.771
File Note: The application submitted by the project proponent has been scrutinized and it was observed that the project proponent has not linked the consent fee with the applications. Accordingly, the project proponent was requested through clarification to link the consent fee. However, the project proponent failed to link the same. As such, the application is returned being incomplete with the request to resubmit the same after linkage of the consent fees.
Inspection: false
Inspection Note:
Officer: PPCBOS63
Reject: true
Reject Note:
Role: RO JEE OS Jasdeep Singh