| File Note: |
Subject: Application for obtaining ‘consent to establish/(NOC) under the Water Act, 1974 and Air Act, 1981–M/s Ecovertex Global Ventures Private Limited Sher-E-Punjab Mill Road, Near Haryana Steel Tubes, Amloh, Fatehgarh sahib.
Ref: Industry's Application ID 30772725 dated 01.01.2026.
The industry has applied for obtaining ‘consent to establish/ (NOC) for establish a new unit for manufacturing of Galvanized Steel Products. The application of the industry has been scrutinized and examined. The facts have also been verified by the
officer of this office during visit to the industry on 15.12.2025 and the details are as under:
A GENERAL INFORMATION
(i) Date of first receipt of application. 01.01.2026
Date of receipt of application complete in all respect. 06.01.2026
(ii) Name & Address of the Industry Ecovertex Global Ventures Private Limited Sher-E-Punjab Mill Road, Near Haryana Steel Tubes, Amloh, Fatehgarh Sahib.
(iii) Raw Materials/Chemicals to be used with quantity Pet bottles scrap@10 MTD
(iv) Products / By Products to Be manufactured with quantity Hot washed pet flakes@9 MTD
(v) Manufacturing Process (flow chart) (Please write the manufacturing process clearly and
do not write that the flow chart is attached) Raw Material > Bale breaker > Feeding Belt > Label Remover > Sorting Belt > Bottle Washer > Inclined Friction Washer-2 > Washing Tank -1& 2 > Floating Tank-1&2 > Inclined Friction Washer-1 > Dryer > Heater Box > Zig Zag Separator > Vibro Separator -Metal Separator > Color Sorter + UV Sorter > Jumbo Bagging> Final Product
(vi) • Total cost of the project
• Cost of plant & machinery. • Rs. 333.50 Lacs
• Rs. 236.00 Lacs.
As per project report submitted by the industry.
(vii) NOC fee Rs. 10800/- vide online receipt no. 540171083 dated 16/10/2025.
Yes, for one year
• Detail
• Whether adequate or not? If yes, for how many years the same is adequate.
(viii) Category of the Industry (Red/Orange
/Green) ORANGE / 152.2 Plastic waste processing (manufacturing of flakes/granules)
(ix) Scale of the industry and the detail of certificate issued by the Competent
Authority regarding Scale of the industry (Small / Medium / Large) Small
(x) Likely date of commissioning November, 2025, yet to be operated
(xii) Land area for which CLU has been obtained from the Competent Authority of the State, in case
applicable NA
(xiv) Proposed source of water supply Own Tubewell (Submersible Pump)
(xv) Competent Authority to decide the case and the circular no. & date vide which the Board has delegated powers to
decide the application. Senior Environmental Engineer
B Coverage of industry under EIA notification dated 14/9/2006 First Schedule of Factories Act, 1948/ Press Note 17 (1984 Series)
(i) Whether the industry is covered under
First Schedule of Factories Act, 1948or N/A
not? If yes, status of clearance of site from Site Appraisal Committee.
(ii) Whether the industry is covered under EIA notification dated 14/9/06 or not? If yes, status of the environmental
clearance. No
(iii) Whether the industry is covered under Press Note 17 (1984 series) or not? If yes, status of environmental clearance
from the State Competent Authority. No
C Location status and siting guidelines
i) Whether industry specific siting
guidelines are applicable or general siting criteria is applicable? General sitting guidelines
are applicable
ii) No. & dated of the notification
/circular
/officer order of the siting criteria applicable to the industry April, 2013
v) Comments of the visiting officer about the suitability of site and construction status:
As per details given below
D Source of Water Pollution and its Control
(i) Trade Effluent Quantity: 6.6 KLD
Mode of disposal: on to land for
plantation after treatment through ETP
(ii) Domestic Effluent Quantity: 1.0 KLD
Mode of disposal: Onto land for Plantation.
(iii) In case mode of the disposal is onto land for irrigation / plantation, give details of land availability and its adequacy. Land availability: Available Whether adequate or not: yes
(iv) Details of Recirculation System Process water : 8.0 KLD will be
recirculated
E Source of Air Pollution and its Control
(i) Sources of Fuel / Process Emissions Steam Gen./ capaci ty Type & Qty. of fuel Stack height (proposed) APCD(proposed)
Above GL. Above RL. Adequacy Type
Hot Water Generator for PET Flakes 600 Kcal/hour Wood briquettes@1000Kgs 15 12 Cyclone Separat or Dust Collection Cyclone & Exhaust Chimney
(ii) Whether the air pollution arrangements proposed by the industry are adequate or not? Adequate in principle
(iii) Whether the boiler furnace will be based on FBC system or not? N.A
(iv) Whether proper canopy has been to install with the D.G. set? NA
F Detail of hazardous wastes to be generated, which are covered under the Hazardous& Other
Wastes
(Management & Transboundary Movement) Rules, 2016 Source of hazardous Quantity to be Category as per Storage / disposal
wastes generated Schedule arrangement
s
-----
G Detail of solid wastes (other than
hazardous wastes) to be generated and the sources there of? Which environmentally sound measures will be
taken for storage and disposal of the same? Source of
Solid wastes Qty.to be
generat ed Storage/
Disposal arrangements
----
H Whether the industry has submitted all documents required for the grant of NOC? (details of documents to be mentioned) yes.
It is submitted that the industry is a small-scale unit and has applied for obtaining Consent to Establish (NOC) under the provisions of the Water Act, 1974 and the Air Act, 1981 for sent up a new unit for manufacturing of Hot washed pet flakes @ 9 MTD by using raw material as Pet bottles scrap@ 10 MTD.
Project Report:
The industry has also submitted the brief project report, wherein, it has mentioned that the total project cost for the proposed Project is Rs. 333.50 lakhs with value of plant & machinery are Rs. 236.00 lakh. Accordingly, the industry has deposited NOC fee of Rs. 10800/- vide online receipt no. 540171083 dated 16/10/2025, which is valid for 01 year as per circular dated 29/10/2018.
Manufacturing Process:
The industry has submitted the manufacturing process, which is as under: Raw Material > Bale breaker > Feeding Belt > Label Remover > Sorting Belt > Bottle Washer > Inclined Friction Washer-2 > Washing Tank -1& 2 > Floating Tank-1&2 > Inclined Friction Washer-1 > Dryer > Heater Box > Zig Zag Separator > Vibro Separator -Metal Separator > Color Sorter + UV Sorter > Jumbo Bagging> Final Product
Feasibility Report:
The industry has proposed to be installed ETP for treatment of domestic effluent, trade effluent generated from the washing process and treated water will be used for plantation.
The industry has also proposed to install Hot Water Generator for PET Flakes using PNG@600 Kcal/hour and Wood briquettes@1000Kgs as fuel in it. It has proposed to install Cyclone Separator as APCD to control the concentration of SPM within the prescribed limits.
Site Suitability:
The industry has submitted Municipal Council, Gobindgarh letter vide No. 1108 dated 11.11.2025 regarding the site of the industry falls under MC limit and also falls under industrial land use zone as per notified master plan of Mandi Gobindgarh. The site of the
industry is suitable for the proposed project.
Applicability of Factories Act, 1948:
The industry is not covered under the Factory Act, 1948.
Applicability of EIA notification dated 14/09/2006
The subject cited industry is not covered under EIA notification 2006 Notification dated 14.09.2006
PWRDA Permission
The industry has mentioned the ground water extraction @ 10 KLD however, the same needs to be as per the consumption. Considering 25 working days in a month, the ground water extraction will be 250 KL/month. As such, the industry is not required to obtain permission for abstraction of ground water from PWRDA.
Visit:
To verify the contents of application the industry was visited by Officers of this Office on 15.12.2025. During visit, it was observed as under:
1. The proposed site of the industry falls in the revenue estate of Village Harbans pura, Distt. Fatehgarh Sahib.
2. The industry has already provided boundary wall around its premises.
3. Plant & machinery proposed by the industry has been arrived at site, but yet o be installed
4. The industry has under installation of effluent treatment plant proposed and treated water will be reused in industrial process.
5. The industry has discharged its domestic effluent into public sewer.
6. The industry has also proposed to install Hot Water Generator for PET Flakes using PNG@600 Kcal/hour and Wood briquettes@1000Kgs as fuel in it. It has proposed to install Cyclone Separator as APCD to control the concentration of SPM within the prescribed limits.
Recommendation
In view of the facts mentioned above, if approved, ZO-II, Patiala may be recommended that Consent to Establish (NOC) under the provisions of the Water (Prevention & Control of Pollution) Act, 1974 and the Air (Prevention & Control of Pollution) Act, 1981 for set up of a new industry for manufacturing of Hot washed pet flakes @ 9 MTD by using raw material as Pet bottles scrap@ 10 MTD, may be granted to the industry for one year with usual suitable conditions.
Competency: Senior Environmental Engineer
|