| File Note: |
• It is submitted that it is a township and area development project. Total area of the project is 35.15 acres and built-up area of the project is 132810.66 sq.m………
• As the total land area of project is less than 50 ha and built-up area is less than 1,50,000 sq.m. Hence, as per MOEF&CC notification dated 29.01.2025, the project is not covered under the ambit of EIA notification 2006 & its subsequent amendments……..
Submitted for approval as earlier recommended by undersigned vide note dated 10.12.2025.........
Competency: Chief Environmental Engineer (Project cost: 16.40 Cr)
|