| File Note: |
On examining the application, RO shall direct the industry to submit compliance of the following SOPs, before proceeding further in the matter:………
1. The industry shall reassess the effluent quantities and make revised agreement with CETP operator, if required, as per the actual generation of effluent and submit the same to the Board.
2. The industry shall prepare a revised lifting schedule with the CETP operator and to ensure that the lifting shall be made atleast 2-3 times in a month and take a written assurance from the operator.
4. The industry shall install CCTV cameras with 30 days backup, facing towards
entry gate of processing shed
flow meter provided on freshwater supply provided for processing activities
effluent storage tanks
any other suitable point deemed fit to ensure that whole of the water consumed is metered and whole of the trade effluent is lifted to CETP operator
The industry shall maintain in-house monitoring mechanism through mobile phone/ office screen for visualizing the above CCTV cameras so as to ensure that no intentional or unintentional lapse happens and no untreated effluent is bye-passed.
5. The industry shall ensure that there is no unauthorized mode of wastewater disposal. ………
6. The industry shall ensure that there is only a single fresh water supply for the industry and meters shall be provided for the water being used for process. ………
7. The industry shall maintain proper record of fresh water consumption and trade effluent generated & effluent got lifted by the CETP operator on daily basis. ……..
8. The record shall be available in the industry at all times, kept in a designated box in the process area to ensure easy and ready accessibility to record keeper as well as regulatory authority. In case, the record is not maintained by the industry, it will be presumed that the industry is disposing of its wastewater illegally and action as deemed fit shall be taken in accordance with law………..
Also RO shall comment on the authorization of CETP operator with whom the industry has carried out lifting agreement and RO is required to intimate the validity sources of air pollution in the industry and the APCD installed and their adequacy. …………………..
If approve application be reverted to RO to do above action
|