| Id: | 30948542 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2026-01-19 15:34:29.152 |
| File Note: | Sir, complete feasibility report is attached herewith. The unit will generate only 0.01 KLD trade effluent which will be treated in batch operations of the ETP. PVC water storage tank has been installed with ETP for storage of treated water and PVC pipe connected on to land for plantation (parks) within its premises. The Plantation area is adequate for disposal of treated waste water. Submitted please. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB191 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Gurvinder Singh |