Show ApplicationProcessingDetails

Id: 30950820
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2026-01-19 18:14:17.759
File Note: The reply of observations raised above is as following: 1. As per approved layout from MC submitted by the project proponent is total saleable area is 9231.69 syd i.e 7718.86 smt now taking maximum FAR as 1:2.1 builtup area comes out to be 16209.6 smt, as such project does not require prior EC for the project. 2. As per feasibility report submitted by the PP it is mentioned that” The treated sewage shall be reused for horticulture & floriculture purposes and remaining will be discharged into municipal sewer”. 3. As per project report submit by the project proponent the project cost is Rs. 335.50 lacs and as such competency of the case lies with Senior Environmental Engineer. Submitted please.
Inspection: false
Inspection Note:
Officer: PPCB217
Reject: false
Reject Note:
Role: RO AEE Manpreet Singh