| Id: | 30954572 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | The application was scrutinized and it has been observed that the industry has not submitted site suitability certificate from revenue authorities. It is therefore requested to submit reply of the clarification within 02 days. |
| Date Created: | 2026-01-20 10:57:29.687 |
| File Note: | The application was scrutinized and it has been observed that the industry has not submitted site suitability certificate from revenue authorities. It is therefore requested to submit reply of the clarification within 02 days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB150 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Bhisham |