File Note: W.R.T to the observation raised by ZO, it is submitted that the PP has submitted revised feasibility report as per which, the total waste water generated is 525 KLD ( unchanged), 220 KLD treated water will be used in dual plumbing and 120 KLD, 45 KLD, 70 KLD treated waste water will be disposed of on to total irrigable green area @>11850 sq. meter in summer, rainy and winter season respectively. The excess treated waste water will be disposed into MC sewer @185 KLD in summer, @260 KLD for Rainy and @235 KLD In winter season respectively………. Submitted for approval, as recommended earlier, Please. (ENCLOSED: Feasibility Report)