| Id: | 30982795 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | While scrutinizing the case, it has been observed that: - 1. The Project Proponent has not submitted a proposal for the disposal of treated domestic effluent and details of the area proposed for plantation/connectivity certificate of sewer from MC, Samrala. 2. The Project Proponent (PP) has not submitted authority letter. 3. The PP has not submitted the certificate from the revenue authority. You are requested to submit the above said observations within 03 days. |
| Date Created: | 2026-01-22 14:48:47.717 |
| File Note: | While scrutinizing the case, it has been observed that: - 1. The Project Proponent has not submitted a proposal for the disposal of treated domestic effluent and details of the area proposed for plantation/connectivity certificate of sewer from MC, Samrala. 2. The Project Proponent (PP) has not submitted authority letter. 3. The PP has not submitted the certificate from the revenue authority. You are requested to submit the above said observations within 03 days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCBOS18 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE OS Manvinder Singh Hundal |