| Id: | 31043818 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2026-01-29 16:46:46.237 |
| File Note: | It is submitted that the application has been scrutinized and observed as under: 1. The industry has not submitted project report. 2. The PP has not submitted the approved building plan. The industry required to clarify the observation within 02 days, but no reply has been received so far. Keeping in view of above, the incomplete application is being returned with suggestions to resubmit the complete application within 07 days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB220 |
| Reject: | true |
| Reject Note: | |
| Role: | RO AEE Harmanpreet Singh |