| File Note: |
In view of above. it is recommended that:-
1. Renewal of consent to operate under Water (Prevention & Control of Pollution) Act, 1974 may be granted to the industry upto 30.09.2031 after correlating with analysis report with usual conditions as per policy of the Board and with special condition that the industry shall comply with the conditions of environmental clearance granted to it.
2. Renewal of consent to operate under Air (Prevention & Control of Pollution) Act, 1981 may be granted to the industry upto 30.09.2031 with usual conditions as per policy of the Board and with special condition that the industry shall comply with the conditions of environmental clearance granted to it. (Competency Chief Environmental Engineer) |