| Id: | 31366901 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | The application of the industry was scrutinized and following descripencies are observed:- 1. The project proponent has not submitted Building Plan approved from the concerned authority. 2. The feasibility report submitted by the project proponent is not upto mark as per other details submit. please clarify the observation within 02 days. |
| Date Created: | 2026-03-03 10:40:17.601 |
| File Note: | The application of the industry was scrutinized and following descripencies are observed:- 1. The project proponent has not submitted Building Plan approved from the concerned authority. 2. The feasibility report submitted by the project proponent is not upto mark as per other details submit. please clarify the observation within 02 days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB122 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Vinod Kumar |