| File Note: | Sir, it is submitted that the industry has submitted the reply to the show cause notice issued to it. It is further submitted that the CETP operator, M/s Bantech Water Ltd., has sufficient capacity to carry the effluent of the industry, as the CETP is presently receiving only about 60–70 KL per day of effluent for treatment against its installed treatment capacity of 300 KLD. Submitted for further necessary action in the matter, please. |