| Id: | 31393227 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | On Examining the application, it has been observed that:- 1. The feasibility report is not properly prepared as no. of plots mismatch with the layout plant, No Builtup area/FAR calculations done and reutilization of waste water is not as per guidelines. The PP is requested to clarify above within 02-days. |
| Date Created: | 2026-03-06 13:30:14.159 |
| File Note: | On Examining the application, it has been observed that:- 1. The feasibility report is not properly prepared as no. of plots mismatch with the layout plant, No Builtup area/FAR calculations done and reutilization of waste water is not as per guidelines. The PP is requested to clarify above within 02-days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB184 |
| Reject: | false |
| Reject Note: | |
| Role: | RO JEE Ranjit Singh |