| Id: | 31398363 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | It is submitted that the application was scrutinized and it was observed that the project proponent has mentioned that the site lies within MC limits, however, it has not submitted site plan/building plan approved by the MC. The PP is requested to clarify it within 03 days. |
| Date Created: | 2026-03-06 19:28:52.478 |
| File Note: | It is submitted that the application was scrutinized and it was observed that the project proponent has mentioned that the site lies within MC limits, however, it has not submitted site plan/building plan approved by the MC. The PP is requested to clarify it within 03 days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB214 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Harblisterjeet Singh |