| Id: | 31501908 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2026-03-18 13:20:51.586 |
| File Note: | Report has been examined and it has been observed that the industry has proposed to provide 10 TPH IF but has failed to submit the feasibility report for control of secondary emission from PSCST and has submitted it from private vendor. If approved, SCN alongwith an opportunity of personal hearing before the CEE (B) of the Board be issued to the industry due to aforesaid violation, pl. Competency: CEE (B) Medium Orange |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB101 |
| Reject: | false |
| Reject Note: | |
| Role: | ZO EE Kamal Singla |